Skip to content

Contingent Decisions

Definition

Contingent decisions are binary choices whose admissibility depends on other choices. If decision 2 is allowed only when decision 1 is yes, the implication is represented by

y2≤y1,y1,y2∈{0,1}.y_2\le y_1,\qquad y_1,y_2\in\{0,1\}.

Interpretation

Contingent decisions model the logical rule "decision 2 is only possible if decision 1 is taken", such as building a warehouse only where a factory is built. With binary variables for the two yes-or-no choices, the rule becomes the linear inequality y2≤y1y_2\le y_1.

A 2 by 2 table of the values of two binary decisions y1 and y2, in which only the combination y1 = 0, y2 = 1 is forbidden by y2 at most y1.

The table lists all four value pairs of (y1,y2)(y_1,y_2). Three of them satisfy y2≤y1y_2\le y_1; only y1=0y_1=0, y2=1y_2=1 fails, since 1≤01\le0 is false. That is exactly the forbidden combination, decision 2 without decision 1. The pair y1=1y_1=1, y2=0y_2=0 stays allowed, so the inequality does not force decision 2 once decision 1 is taken.

Checking every value combination, as in the table, is the general way to design and verify such constraints. In words, y2≤y1y_2\le y_1 says "if y2=1y_2=1 then y1=1y_1=1", or equivalently "if y1=0y_1=0 then y2=0y_2=0". If instead decision 2 must be taken whenever decision 1 is, the reverse inequality y1≤y2y_1\le y_2 is needed, and requiring both gives y1=y2y_1=y_2.

A common slip is to read y2≤y1y_2\le y_1 as a two-way link. It only rules out "2 without 1"; whether decision 2 is taken when decision 1 is depends on the objective and the other constraints. Rules with several conditions are built from several such inequalities, one per condition, as in the Key Results. Mutually exclusive decisions express a different rule, "at most one", with a sum. Both kinds of rule can be added to a project selection model when projects depend on or exclude each other.


Key Results

  • If decision 2 must be yes when decision 1 is no, use y1+y2≥1y_1+y_2\ge1.
  • If decision 3 is allowed only when both decisions 1 and 2 are yes, use y3≤y1y_3\le y_1 and y3≤y2y_3\le y_2.
  • If y1=1y_1=1 and y2=0y_2=0 must imply y3=0y_3=0, use y1−y2+y3≤1y_1-y_2+y_3\le1.

Examples

  • With binaries WLA=1W_{LA}=1 if a warehouse is built at location LA and FLA=1F_{LA}=1 if a factory is built there, WLA≤FLAW_{LA}\le F_{LA} requires a local factory before a warehouse can be built.
  • y1+y2+y3≤2y_1+y_2+y_3\le2 rules out all three yes decisions together.

Prerequisites

Sources

Symbols: element of