Skip to content

Effective Lead Time

Definition

For a repeating EOQ ordering cycle of length t0∗>0t_0^*>0 and fixed lead time L≥0L\ge0, the effective lead time is

Le=L−nt0∗,n=⌊Lt0∗⌋.L_e=L-nt_0^*,\qquad n=\left\lfloor\frac{L}{t_0^*}\right\rfloor.

Thus 0≤Le<t0∗0\le L_e<t_0^*. The course's on-hand reorder level is DLeDL_e.


Interpretation

The effective lead time says where in the stock cycle an order must be placed when the delivery delay is longer than one cycle. Whole cycles inside the delay do not change the position in the sawtooth, so only the remainder LeL_e matters for the reorder level.

A sawtooth stock level over 28 weeks with a reorder level line; an order is placed at week 1 and arrives 20 weeks later, after two full cycles and an effective lead time of 6 weeks.

The cycle lasts 77 weeks and the delay L=20L=20 weeks. The order placed at week 11, when stock has fallen to 6D6D, arrives at week 2121: it spans the remainder Le=6L_e=6 weeks plus n=2n=2 full cycles. Placing the order 66 weeks before some stockout is therefore the right moment, even though the stockout it serves lies 2020 weeks ahead.

Whole cycles inside LL do not matter for the reorder level: only Le=L−nt0∗L_e=L-nt_0^* does. Make LL longer than a cycle to see orders overlap.

The number n=⌊L/t0∗⌋n=\lfloor L/t_0^*\rfloor is the floor of L/t0∗L/t_0^*: the number of complete cycles that fit into the delay. Subtracting them leaves 0≤Le<t0∗0\le L_e<t_0^*, so the reorder level DLeDL_e is always below the batch size y∗y^* and is actually reached by the on-hand stock. With L<t0∗L<t_0^*, nothing is subtracted and Le=LL_e=L.

A common slip is to use DLDL as the reorder level when LL exceeds a cycle: in the figure, DL=20DDL=20D is far above the maximum stock y∗=7Dy^*=7D, a level the on-hand stock never reaches. The physical delay is still LL: LeL_e only fixes the ordering moment, and when an order is placed, nn earlier orders are still on their way, as in EOQ with lead times.


Key Results

  • For a lead time shorter than a cycle, Le=LL_e=L.
  • The quantity LeL_e is a cycle remainder, not a shorter physical delivery delay.
  • If the delay is an exact multiple of the cycle, the remainder is zero; ordering and receipt events must be interpreted at that common cycle boundary.

Examples

  • In the figure, time is measured in weeks. A cycle of t0∗=7t_0^*=7 weeks gives y∗=7Dy^*=7D. With L=20L=20 weeks, n=2n=2 and Le=20−2⋅7=6L_e=20-2\cdot7=6 weeks, so the reorder level is 6D6D. The order placed at week 1 arrives at week 21; two earlier orders are still in transit when it is placed.
  • The snack bar has L=12L=12 days and t0∗≈4.83t_0^*\approx4.83, giving Le≈2.34L_e\approx2.34 days.

Prerequisites

Sources

Last updated: 20 October 2026 03:02